Earthworks, undercut and backfill to subgrade, stormwater drainage, and aggregate supply to widen the runway and shoulders to civil aviation regulations including extending the apron areas.  Responsible for the quality and supply of pavement aggregates to the pavement construction crew (Hiway Stabilizers). Overall Construction Project Management.

5 Months

Duration

November 2008

Completed

Andrew Naylor